Customer Order Life Cycle

POSI & TRUSSES

POSI & TRUSSES PRODUCT SCHEDULE

TIMELINE PROCESS

STEP 1 - Customer Request

  • Logged on ATE Platform

  • Sales & Design Lead Assigned

STEP 2 - Preliminary Design & Quotation Issued

  • Valid for 4 weeks.

  • Terms and Conditions of sales issued and accepted.

STEP 3 - Order Confirmed by Client

  • 50% of the Deposit to be paid.

  • Delivery Date to be confirmed.

  • Site /details to be confirmed (Eircode, Contract manager, etc.)

STEP 4 - Site Visit by ATE

  • Site Measurements were taken.

  • Architectural issues addressed.

  • Design Review.

STEP 5 - Design Freeze

  • Quotation.

  • Design drawings issued to production.

  • No changes allowed.

STEP 6 - Production

  • Production Schedule Locked.

  • Balance of Payment due two weeks before delivery.

  • Delivery Schedule Locked.

  • Change penalties apply at 5% of order value.

STEP 7 - Trailer Loading

  • 100% Payment completed.

  • Site Readiness confirmed.

STEP 8 - Delivery To Site

  • Laydown Area available.

  • Crane in place.

  • Scaffolding.

Do You Have More Questions Regarding the Posi Joist & Roof Trusses Schedule & Timeline?

Let’s Get Through This Together!

Different Time Lines & Payment Details

From Enquiry to Design freeze (min 5 weeks)

Trusses & Posi Joist Product Timeline from Design Freeze to Delivery on Site = 2 weeks (10 working days) 100% Payment prior to delivery to site.

5% Penalty for changes after Design Freeze (in either the Schedule or the Design)

Dispatch & Delivery on the same day in Ireland.

UK delivery is 7 days after the dispatch date.